Here is a look at the timeline of how council came about its decision for the plan for cast iron water main replacement.
Feb. 9, 2015 – Council adopted
a resolution to authorize the development of a long-term policy on cast iron
water main replacement as well as near-term funding options for it.
March 17-31,
2015 – The City of Moose Jaw held cast iron water main replacement
program public consultations and presented seven funding options for public
input, online during this entire period and in-person on March 17, 18 and 19.
The highest percentage of consultation results were 49 per cent for funding
using various sources, 43 per cent for using a portion of city reserves and 40
per cent for a local improvement program (LIP).
May 4, 2015 – Council
authorized city administration to proceed with the required steps to establish
a non-petitionable local improvement program to cover 30 per cent of the cost
of water main replacement in the city.