Moose Jaw Times-Herald: Council notebook

Council is seen at the June 24, 2013 meeting at city hall.
Times-Herald photo by Lisa Goudy
By Lisa Goudy


In the 35th update on the multiplex there were no changes from last month.

Director of parks and recreation Jody Hauta presented the report to council at Monday’s meeting. He said the close out procedures are still underway at Mosaic Place and YaraCentre within the approved budget of approximately $61.29 million. A total of $281,492 is in the project contingency, same as last month.

Other items discussed at Monday’s meeting:

• Council approved two decisions of the development appeals board for Robinson Contracting Ltd. to have variances on two properties on the 100 block of Everton Cres.

• Council approved the reports of the recent meetings of the personnel committee on June 12, 13 and 18.