There are 12 items left on the deficiency and warranty list for Mosaic Place.
Hockey Capital Moose Jaw Ltd. (HCL) are
primarily working on heating levels in the curling rink, including
enhancements to
the system, and dealing with inconsistent lighting in the arena,
mostly under the score clock. New lighting has been installed
and so have lenses under the score clock.
All of the warranty and deficiency items for YaraCentre have been completed and HCL has been paid out. Landscaping around
the installation of catch basins on the storm sewer on the east side of the building will be finished this spring.